About six times more renewable capacity is waiting to be connected to the grid than was installed in the European Union last year.
EnvironmentEuropean Union
- Omissions
- The 'six times' ratio is a rounded rhetorical figure published by the European Investment Bank (EIB) in its communication piece, not a precise Eurostat/ENTSO-E statistical series; the exact basis of the ratio is not disclosed in the source.
- The EIB source speaks of 'Europe', whereas the claim specifies the 'European Union' (EU-27) — a slight geographic scope difference.
- Independent data on grid-connection queues point to a potentially larger figure than six times: Ember reports 'almost 700 GW' stuck in connection queues across eight reporting countries, while Beyond Fossil Fuels/E3G report about 1,700 GW of renewable and hybrid projects waiting across 16 countries (2024-2025). Because these cover different country sets and project definitions, they cannot be directly equated with the EIB ratio, but they suggest the real multiple may exceed six rather than fall short of it.
- Some sources found (Ember, Beyond Fossil Fuels, E3G) are dated 2025; the EIB page has been updated to reference 2025 installed capacity, so the precise publication date of the EIB page could not be confirmed.