In 2024, emergency interventions for managing overloaded electricity networks cost approximately 4.3 billion euros.
Industry & EmploymentEuropean Union
- Omissions
- The MEP did not cite the source: the figure comes from ACER's 2025 report on cross-zonal electricity trade and congestion management.
- The term 'emergency interventions' is a paraphrase of ACER's technical term 'remedial actions,' which encompasses redispatch, countertrading, and curtailment measures taken by TSOs to relieve grid congestion.
- The €4.3 billion covered 60 TWh of remedial actions — equivalent to Austria's annual electricity consumption — providing context on the scale of the problem.