The three most recent nuclear power plant projects in Europe (Finland, France, UK) took an average of 17 years from start to production.
EnvironmentSpain
- Error detected
- Hinkley Point C is not yet producing power as of March 2026, making the claim factually incorrect
The claim includes a plant (Hinkley Point C) that is still under construction in the 'average time until producing power' calculation
- Omissions
- The claim fails to specify that the calculation method includes plants that only recently became operational and one that is still under construction
- The claim omits that Olkiluoto 3 started commercial operation on May 1, 2023, not earlier
- The claim omits that Flamanville 3 was connected to the grid in May 2024
- The claim omits that Hinkley Point C is still under construction with expected completion in 2025-2027
- The three plants use the same EPR (European Pressurized Reactor) design, which experienced significant delays - this is not representative of all nuclear projects